The Pinkham fish passage restoration project along Carpinteria Creek, represents one of the last barriers in the Carpinteria Creek Watershed. The project will replace an undersized rail car bridge with a wider and taller bridge. It will also remove 90 feet of concreted stream channel and banks. The stream channel will be regraded and the creek banks will be restored with native riparian vegetation. When the project is complete steelhead trout will have access to upstream habitat.
Friday, October 18, 2013
Project Update -1
The Pinkham fish passage restoration project is underway. The contractor mobilized to the site last week and began demolishing the concreted channel and existing bridge. This week all of the demolished materials were removed from the site. The contractor then began to excavate on either side of the creek at the location where the new bridge abutments will be constructed. Screened and properly compacted soil has been added to the base of the excavated area and forming of the new abutments should begin next week.
Earlier in the week Shaw contracting worked to remove the last of the concrete from the stream. Large rocks that were grouted into the stream banks and found in the channel will be reused in the new stream channel and rock slope protection later on in the project.