Friday, November 15, 2013

Project Update - 5

This week the wood forming around the abutments was removed. Once the concrete had set and reached the correct strength the contractor began back filling behind the abutments. This will continue into early next week. The California Conservation Corps will be out next week to help bolt and secure the log structures. The contractor will finish up the stream channel and begin placing the rock slope protection around the abutments.


The contractor beginning to fill in behind the southern abutment (far abutment).  The fill material is compacted and inspected in lifts.










By the end of the week the contractor was nearly finished filling in behind the south abutment.

Check back next week for more updates.