Shaw Contracting working to place rock around the abutments and build up the new stream channel.
The California Conservation Corps working to apply epoxy to secure and anchor the large woody debris structures.
The California Conservation Corps working to apply epoxy to secure and anchor the large woody debris structures.
Willow poles that were installed a few weeks ago are already sprouting.
The project is on schedule for the bridge delivery during the first week of December. Check back next week for more updates.